Raised access floor installation at the Transtelecom telecommunications center, Astana

Projects — Data centers & server rooms

Transtelecom Telecommunications Center, Astana

Role
Supply + installation
Area
338 m²
Year
2020

Object

The Transtelecom telecommunications center in Astana. The client of DIVIO was the system integrator Genesis Engineering. DIVIO supplied the raised floor system and installed it across 338 m². Year — 2020.

Transtelecom telecommunications center: panel installation, some cells still open

Scope

Area — 338 m², finished floor height — 450 mm.

The panel covering is 3 mm antistatic rubber — a special solution for the requirements of the site. The panels were supplied with this covering already applied.

Substructure with stringers around a column
338m²

Raised floor area in the telecommunications center.

450mm

Finished floor height.

3mm

Antistatic rubber on top of a calcium sulphate panel — a special solution for the requirements of the site.

Structure

The panel is high-density calcium sulphate, 1600 kg/m³, 30 mm thick, with 3 mm antistatic rubber on top. The galvanized steel substructure was assembled with reinforced stringers and fixed to the subfloor.

The schematic below shows a section with the floor height and stringers, the panel build-up, and the area in 600 × 600 mm modules.

Floor section

600450 mm1234
  1. 1Panel 600 × 600 mm
  2. 2Stringer
  3. 3Pedestal
  4. 4Subfloor
  5. Floor height — 450 mm

Panel · 600 × 600 mm

  1. 01Antistatic rubber, 3 mm
  2. 02Calcium sulphate 1600 kg/m³, 30 mm

Area in 600 × 600 mm modules

338 m²

  • 600 × 600 mm module
DIVIO schematic, not a working drawing. Dimensions, areas, and quantities follow the project documents; the module arrangement is schematic.

A standalone service

Raised access floor engineering

Load calculations, structure and core selection, the layout grid, specifications and drawings. Available without installation.

Order engineering

Works

The work went in order: priming the concrete subfloor, assembling the substructure with reinforced stringers and fixing it to the subfloor, laying the panels. DIVIO also supplied the system.

Site
Transtelecom telecommunications center, Astana
Client of DIVIO
System integrator GENESIS Engineering Project Management
Area
338 m²
Floor height
450 mm
Panel
600 × 600 mm, calcium sulphate 1600 kg/m³, 30 mm
Covering
Antistatic rubber, 3 mm
Substructure
Galvanized steel, reinforced stringers, fixed to the subfloor
Subfloor
Concrete priming
Year
2020
DIVIO role
Supply and installation

Your next site

Need a raised floor for a server room?

Tell us the area, height and equipment loads — we'll select the system class and work out the specification.